2019年8月29日星期四

Customer site technical guidance – nitrogen production equipment

Suzhou Xinglu Air Separation Plant Science and Technology Development Co., Ltd.(“XLA” for short) mainly is engaged in R&D, design and manufacture in cryogenic technology filed, equipment leasing and device maintenance. Through 30 years` development, XLA has grown to the pioneer of R&D and design of cryogenic air separation technology in China. XLA has been granted Certificate of ISO9001, ASME Certificate of Authorization, NB Certificate of Authorization, “U” Stamp etc. international qualification certificates and CE product certificate. Customers throughout the country and exported to the Americas, Europe, Asia and Africa, more than 40 countries.
Our company signed a contract to supply nitrogen plant in Turkey in 2017. This set of plant is in accordance with CE standard. In early June 2018, the equipment was successfully debugged and has been running normally for more than a year. During normal operation, the plant is controlled automatically, no operators are required at Jobsite, the capacity control during normal operation can be set remotely. This plant power consumption is low. The power consumption reaches 0.22kwh/Nm3.
Nitrogen plant
According to the current situation of gas product demand at the customer’s site, the oil free screw compressor adjustable range larger. The capacity of gas nitrogen is adjustable from 1000Nm3/h~2000Nm3/h. And the variable load adjustment is automatic.
Our company has a first-class technical guidance team. Since the installation of the equipment, our technical engineers have provided various trainings to the on-site operators of the users, covering the standard operation of the equipment and daily maintenance.
At the same time, our company not only provides a set of detailed instructions for users to use for reference, but also gives video guidance in the process of customer operation, so as to better serve customers in detecting the operation status of equipment.Users appreciate our debugging and guidance work very much and invite our company to do maintenance and guidance work on site regularly every year.
The following photo showing the Atlas engineer is doing the remote setting program adjustment.

(source:Air separationhttps://www.airseparation-plant.cn/customer-site-technical-guidance-nitrogen-production-equipment/)

2019年8月6日星期二

Early July of 2019, India project third shipment – whole set of equipment delivery from XLA

After the second shipment of goods were delivered in the middle of June, the third shipment of cold boxes left XLA`s factory in early July. XLA have many times meetings with this India project customer for the plant designed in the early stage, and after many discussions, negotiations and modifications,we two parties finally signed the purchasing contract in July 2018. After a year of intensive and orderly professional production and manufacturing, the delivery and loading of the third shipment of main cold box had successfully completed by the end of this month.
The cold box is tightly packed and covered with rainproof cloth in XLA factory. XLA has more than 30 years of production and design experience in the field of air separation, as well as rich experience in loading and delivery. The equipment loading process in the workshop is guided by the company’s professional masters, and the ropes are also specially fixed in order to avoid too much shaking and collision during transportation. XLA will look for large-scale shipping companies with professional experience in exporting air separation plant for storage and transportation, and require the personnel of the freight forwarding company to participate in the loading process in the company’s workshop so as to better understand the loading and lifting process.
The third shipment of equipment successfully arrived at Shanghai port in Mid-July. Below are the photos of unloading from the truck and loading provided by the forwarder.
FIG. 1 all the people work together to connect the lifting rope and equipment;
FIG. 2 slowly lift the equipment and move it onto the ship;
FIG. 3 fixed equipment after loading;
FIG. 4 shows the successful completion of equipment fixation.
During this period, under the guidance of the professional personnel trained by XLA, who will make joint efforts to ship the equipment safely.
Air separation
The upper section and the lower section of the cold boxes were lifted and loaded onto the ship respectively by the site staff. These two sections of cold boxes were designed and produced by XLA and assembled on the jobsite. Due to the large equipment, the designers designed in two sections to facilitate transportation.
Air separation plant Manufacturer
In the evening of the same day, all the third shipment of goods were loaded into the ship by lifting and other means with the full cooperation of the on-site personnel. It took seven hours to complete the loading and was already to ship to India. The next step is to wait for all the equipment to arrive at the customer’s jobsite in India, and after confirm with customer XLA will send professional engineers to guide the installation of the equipment.
Hope everything goes well! This plant is also about to be another successful case of plant in the Indian market.

(source: https://www.airseparation-plant.cn/early-july-of-2019-india-project-third-shipment-whole-set-of-equipment-delivery-from-xla/)

2019年7月25日星期四

Middle June 2019 India project- second shipment of equipment

Among the air separation plant exported from China to India, Xinglu Air Separation plant ranked the forefront. XLA has 25 sets of equipment exported to India projects guidance and installation experience . Among them, INOX AP group, a famous Indian manufacturer of air separation, has purchased 11 sets of air separation plant from our company successively, which still maintains a good cooperative relationship at present, and keeps inquiring for new plant every month. Xinglu leading design and plant efficient and stable operation. XLA has been enjoying a high reputation in the field of air separation in India, which is also the first choice for many new and old customers to add new plant projects.
Bellow is the news about Middle June 2019 India project- second shipment of equipment
The picture on the left shows that the workshop workers are carefully polishing the adsorption vessel without missing any details.
The picture on the right shows the adsorption vessel after painting.
Air separation








As for the painting work after the completion of the equipment, XLA has its own independent and professional painting room, and the painting work in the workshop is carried out in the dust-free painting room. Automatic computer control paint room has first-class advanced painting technology and professional operation workers, each plant out of factory is of high standard.
The picture shows the adsorption vessel finished painting, waiting for packaging in the packaging area for loading and delivery.
Air separation plant Manufacturer











The picture shows the left and right adsorption vessels after packing tightly. XLA will do a good job in painting the sign of equipment placement direction on the outer packing of waterproof cloth for equipment to remind customers, so as to avoid accidents in the unloading process and avoid causing damage to the adsorption vessel support. Air separation plant






The second batch of goods out of XLA smoothly and will arrive at the customer’s job site one month later. Looking forward to the smooth assembly of plant, after commissioning, first successful start up.
Please refer to the air cooling tower and adsorption vessels video out of factory.


(source: https://www.airseparation-plant.cn/middle-june-2019-india-project-second-shipment-of-equipment/)

2019年7月10日星期三

The Russian customer participated in the XLA loading-The first day

In the morning of June 20, 2019, in Xinglu Air Separation’s workshop, the loading staff worked together to lift the close loop cooling tower lower case body and load the car. Under the professional guidance of director of our company and the cooperation of the on-site staff, the car was loaded successfully! At the same time, a Russian engineer and forwarder are on site to conduct loading inspection and take photos.
Air separation
The picture shows ladder platform loading
Air separation plant Manufacturer
As can be seen in the picture, the water cooling tower was lifted by the crane, moved slowly and placed carefully.
liquid oxygen plant
XLA has more than 30 years of design and manufacturing experience, and the workshop packaging director has also worked at XLA for more than 20 years. According to his rich loading experience and professional guidance. XLA can ensure that the equipment is in the best condition from production to transportation, from the factory to the customer’s project installation site.
Please refer to the water cooling tower loading truck video for details.


(source:https://www.airseparation-plant.cn/the-russian-customer-participated-in-the-xla-loading-the-first-day/)

2019年7月2日星期二

SNEC 13th(2019)International Photovoltaic Power Generation and Smart Engergy Conference& Exhibition 2

Mr. Xue Lu, chief manager of Xinglu, came to this exhibition to exchange argon recovery plant with customers. Xinglu is the founder of crude argon recovery in photovoltaic industry and the pioneer of deep utilization of crude argon recovery.
Air separation
Chief manager Mr. Xue Lu and domestic trade manager introduced crude argon recovery plant to the customer. The plant was put into production in July 2018. It is the world’s first crude argon recovery and purification device for oil-containing polycrystalline silicon industry, which not only reduces the production cost of end users, but also creates a pioneer in the field of cryogenic plants.
Air separation plant Manufacturer
Domestic trade manager of XLA and senior technical staff are explaining to the customer our company’s first set of argon recovery plant, which is developed for the monocrystalline silicon photovoltaic product manufacturer and is now in stable operation, adopting a number of patented technologies and modular design. It was successfully started in December 2018.
Air separation plant
The manager of overseas department introduced the process of argon recovery and purification to the foreign customers, and the customer is impressed by our advanced technology.
Air separation plant suppliers
This exhibition is a complete success, thanks to Shanghai photovoltaic exhibition for providing this platform, which makes XLA shine in the publicity of argon recovery plant.
XLA will always adhere to the development policy of “Convenience, Reliable and Energy-saving are our devotion and pursuit “, and do better in the field of air separation plant!
(source:https://www.airseparation-plant.cn/snec-13th2019international-photovoltaic-power-generation-and-smart-engergy-conference-exhibition-2/)

2019年6月11日星期二

SNEC 13th(2019)International Photovoltaic Power Generation and Smart Engergy Conference& Exhibition 1

The 13th SNEC (2019) exhibition opened at the Shanghai new international expo center in pudong on June 4, 2019. Xinglu Air Separation Plant enjoyed the privilege of participating photovoltaic exhibition! In the solar photovoltaic industry, argon gas has always taken a large proportion of the production cost, and how to reduce the cost of argon gas has become the key to improve the competitiveness of the solar photovoltaic industry.
Air separation plant Manufacturer
From 2005, XLA has made in-depth research on the use of argon in solar photovoltaic industry. After a large amount of technical and financial investment, the first generation of crude argon recovery and purification device was successfully developed in 2007. After years of R&D and innovation, the second generation and the third generation of crude argon recovery, purification devices have been put into operation successively in 2017-2018 respectively, which marks that the crude argon recovery and purification device developed and produced by XLA has become mature and has entered the market in an all-round way.
Air separation plant suppliers
In this photovoltaic exhibition, customers are interested in Xinglu argon recovery equipment, which is also an important reason of Xinglu was invited to participate in this exhibition. Only Xinglu can realize this technology in the whole exhibition hall, which indicates Xinglu’s originality in the field of air separation, strong independent R&D and high innovation ability.
 (source:https://www.airseparation-plant.cn/snec-13th2019international-photovoltaic-power-generation-and-smart-engergy-conference-exhibition-1/)

2019年6月10日星期一

Plant first time start-up is success, XLA deserves the honor

At the beginning of 2019, the plant purchased by a Jiangxi gas company was successfully started up after installation and commissioning.
Air separation
On May 12, 2019, the customer of the gas company came to Suzhou XingLu Air Separation Plant company specially to deliver our company the praise brocade banner, which was praised for “Excellent technology, high production and low consumption”. The picture shows Mr. Xue Lu, general manager of our company taking the customer’s brocade banner and taking a photo in Suzhou Xinglu company.
Suzhou xinglu adhering to the “Convenience, Reliable and Energy-saving are our devotion and pursuit” principle of operation.
(source:https://www.airseparation-plant.cn/plant-first-time-start-up-is-success-xla-deserves-the-honor/)

Nitrogen plant